What it is A horizontal timeline of your phases and tasks, with bars you can drag to reschedule.

Reading the timeline

  • Each phase is a swimlane; tasks sit inside it.

  • Bars show a progress fill so you can see completion at a glance.

  • Single-day items appear as milestone diamonds.

  • Tasks with no valid dates drop into an Unscheduled tray so nothing silently disappears.

Scheduling

  • Drag a bar left/right to move a task, or drag its edges to change duration. Changes save automatically.

  • Use the zoom control to switch between Day / Week / Month / Quarter scales.

Toggles at the top of the Gantt

  • Critical Path — highlights the longest chain of dependent tasks driving your end date (on by default).

  • Show Baseline — overlays ghost bars of your saved plan so you can compare planned vs. actual (see Baselines).

  • Show Products — adds product-related items to the timeline; hover the tooltip for details.

Deliveries Product arrival dates appear in a Deliveries lane, grouped by room/location, so procurement and the schedule live in one place.